Hastings Deering Toowoomba

IndustrialInfrastructure
Site

15-17 Carrington Road, Toowoomba, QLD 4350

Specifier

GHD Toowoomba

Contractor

Northbuild Construction

Description

The design for this site involved had to meet the requirements of QLD’s State Planning Policy SPP4/10, however, due to the site constraints had to have no land take and needed to be located within 20m from a retaining wall. The design was augmented with a ChamberMaxx system to help provide extra detention for the StormFilter to obtain the load based reduction targets.

Maintenance

The EnviroPods expected to be maintained once every 3-6 months whilst we estimate that the StormFilter technology should require maintenance every 18 months. The system should still be checked within