Masters – Marsden Park

CommercialInfrastructure
Site

Marsden Park NSW 2765

Specifier

Henry & Hymas

Contractor

Quasar Construction

Description

This project was designed by Henry and Hymas Consulting Engineers and is in the Blacktown LGA. Water quality targets are 85/65/45 and MUSIC modelling was required. The site is predominantly made up of warehousing and car park areas hence Enviropods have been used as the primary form of pre-treatment to capture key pollutants such as Suspended Solids. The StormFilter cartridges are located downstream of the EnviroPods within a precast vault tank were additional storage has been implemented.

Maintenance

The 82 Cartridge StormFilter system is designed to achieve an annual maintenance frequency with EnviroPods to be serviced every 3-6 months. Periodic inspections and cleans are also scheduled to take p